Solution: How long would it take Dan to do a certain piece of work alone?

It takes Butch twice as long as it takes Dan to do a certain piece of work. Working together they can do the work in 6 days. How long would it take Dan to do it alone? How to solve work problems?

How long would it take Dan to do it alone?

Problem Statement: CE Board November 1993

It takes Butch twice as long as it takes Dan to do a certain piece of work. Working together they can do the work in 6 days. How long would it take Dan to do it alone?

Problem Answer:

Dan would take 9 days to finish the work alone.

Solution:

Online Questions and Answers in Age, Work, Mixture, Digit, Motion Problems