Solution: How long will they finish the job working together?

If A can do the work in “x” days and B in “y” days, how long will they finish the job working together? How to solve work problems?

How long will they finish the job working together?

Problem Statement: ME Board April 1995

If A can do the work in “x” days and B in “y” days, how long will they finish the job working together?

Problem Answer:

Together, they will finish the job in n = xy/(x+y).

Solution: