Solution: How many workers are needed in an assembly line?

The average rate of production of transistors is 12 units for every 2 hours work by 3 workers. How many workers are needed in an assembly line working 40 hours each week with a weekly production of 800 transistors?

How many workers are needed in an assembly line?

Problem Statement:

The average rate of production of transistors is 12 units for every 2 hours work by 3 workers. How many workers are needed in an assembly line working 40 hours each week with a weekly production of 800 transistors?

Problem Answer:

5 workers are needed in an assembly line working 40 hours each week with a weekly production of 800 transistors.

Solution:

Latest Problem Solving in Age, Work, Mixture, Digit, Motion Problems

More Questions in: Age, Work, Mixture, Digit, Motion Problems

Online Questions and Answers in Age, Work, Mixture, Digit, Motion Problems


Search! Type it and Hit Enter


We educate thousands of students a week in preparation for their licensure examinations. We provide professionals with materials for their lectures and practice exams. To help us go forward with the same spirit, contribution from your side will highly appreciated. Thank you in advance.


Post a Comment

Contact Form

Name

Email *

Message *

Powered by Blogger.
Javascript DisablePlease Enable Javascript To See All Widget
Real Time Web Analytics