Solution: How many workers are needed in an assembly line?

The average rate of production of transistors is 12 units for every 2 hours work by 3 workers. How many workers are needed in an assembly line working 40 hours each week with a weekly production of 800 transistors?

How many workers are needed in an assembly line?

Problem Statement:

The average rate of production of transistors is 12 units for every 2 hours work by 3 workers. How many workers are needed in an assembly line working 40 hours each week with a weekly production of 800 transistors?

Problem Answer:

5 workers are needed in an assembly line working 40 hours each week with a weekly production of 800 transistors.

Solution:

Latest Problem Solving in Age, Work, Mixture, Digit, Motion Problems

More Questions in: Age, Work, Mixture, Digit, Motion Problems

Online Questions and Answers in Age, Work, Mixture, Digit, Motion Problems


Search! Type it and Hit Enter


Accepting Contribution for Website Operation. Thanks!

Post a Comment

Contact Form

Name

Email *

Message *

Powered by Blogger.
Javascript DisablePlease Enable Javascript To See All Widget